Activity Predecessor Optimistic Pessemistic Expected Variance A 2 6 4 0.44 B 1 9 3 1.78 C A 2 6 4 0.

Activity Predecessor Optimistic Pessemistic Expected Variance A 2 6 4 0.44 B 1 9 3 1.78 C A 2 6 4 0.44 D B 5 17 9 4 E C 3 11 5 1.78

a)      How many weeks should John Black allow for completion of the project if he is comfortable with only a 2.5% chance of being late?

 